- The technique most commonly used by project management software packages to construct a project schedule network diagram is:
- Activity-On-Node (AON)
- Finish-to-Start (FS)
- Activity-In-Node (AIN)
- Node-On-Activity (NOA)
Forums:


krantikumar50
Tue, 07/24/2012 - 07:02
Permalink
Answer
Hi Ramana,
The answer is "A" or AON.
B is dependency.
C and D are fake/made up terms.
Warmly, KK....
Ramana_99
Tue, 07/24/2012 - 08:06
Permalink
correct
You are correct, I bit confused about A and B.
However, A is the correct answer.
Regards,
Ramana
krantikumar50
Tue, 07/24/2012 - 08:14
Permalink
Nothing
Hi Ramana,
There is nothing to be confused about. "A" is the only schedule network diagramming technique in the 4 listed options.
Finish to start, start to finish etc, these are all dependency determination. Meaning, let this be done then will do that and then that and then that.
C and D are made-up terms. Forget about it.