Tyler has 3 activities to be completed in his project. Activity A has a duration of 5 days and starts on March 5th. Activity B has Finish-to-start with 2 days lag relationship with activity A. Activity C has Finish-to-start with 3 days lead relationship with activity B. The project will be completed on?
March 21st
March 18th
mARCH 17TH
MARCH 22ND
Forums:


dipti1pmp
Sun, 10/05/2014 - 06:51
Permalink
NOTE
NOTE ALL activities have a duration of 5 days
admin
Wed, 10/08/2014 - 11:10
Permalink
The time between start dates
The time between start dates of two tasks is defined as Lag
If task can be started prior to another task its called 'lead'
Activity A + 2 days + Activity B = Completion
Activity C will be started 3 days before B and will be complete so its not on critical path.
5 + 2 + 5 = 12 days
5th March + 12 days = 17th March