QUESTION

Tyler has 3 activities to be completed in his project. Activity A has a duration of 5 days and starts on March 5th. Activity B has Finish-to-start with 2 days lag relationship with activity A. Activity C has Finish-to-start with 3 days lead relationship with activity B. The project will be completed on?

March 21st
March 18th
mARCH 17TH
MARCH 22ND

NOTE ALL activities have a duration of 5 days

admin's picture

The time between start dates of two tasks is defined as Lag

If task can be started prior to another task its called 'lead'

Activity A + 2 days + Activity B = Completion

Activity C will be started 3 days before B and will be complete so its not on critical path.

5 + 2 + 5 = 12 days

5th March + 12 days = 17th March