Q. Risk response
Submitted by y0zh on Thu, 04/25/2013 - 13:56
As part of risk planning, some responses are designed for use only if certain events occur. A project manager of a multi-year project decided to trigger one such set of responses during the Monitor and Control Risks phase. Which of the following is likely to have triggered the responses?
Late receipt of status reports
A key employee going on vacation for three days.
Errors found in a deliverable document
Missing an intermediate milestone
Forums:


BK
Thu, 04/25/2013 - 14:05
Permalink
B
B
crushPMP
Thu, 04/25/2013 - 14:32
Permalink
A?
A?
y0zh
Thu, 04/25/2013 - 14:40
Permalink
answer in test: D - Responses
answer in test:
D - Responses designed for use only if certain events occur are known as contingent response strategies. These responses are triggered by events such as missing intermediate milestones. The other events listed may not warrant triggering of contingency responses. [Refer PMBOK 4th Edition, page 305] [Project Risk Management]