Q. Risk response

As part of risk planning, some responses are designed for use only if certain events occur. A project manager of a multi-year project decided to trigger one such set of responses during the Monitor and Control Risks phase. Which of the following is likely to have triggered the responses?




  1. Add a note hereLate receipt of status reports



  2. Add a note hereA key employee going on vacation for three days.



  3. Add a note hereErrors found in a deliverable document



  4. Add a note hereMissing an intermediate milestone


 

 B

crushPMP's picture

A?

answer in test:


D - Responses designed for use only if certain events occur are known as contingent response strategies. These responses are triggered by events such as missing intermediate milestones. The other events listed may not warrant triggering of contingency responses. [Refer PMBOK 4th Edition, page 305] [Project Risk Management]