Your subcontractor delivered building raw material 3 days late. To bring some degree of satisfaction, he reduced its cost by 5%. This offer is an example of?
Options:
A: Compromise
B: Collaborate
C: Smoothing
D: Forcing
Forums:


HazS
Wed, 12/16/2015 - 07:23
Permalink
I would say it's Compromise
I would say it's Compromise (A),
Because it's a lose-lose situation, he lost money, and you lost time,