Resource optimization

I am not understanding the difference between both and how to decide this in scenario based qts?

Any thoughts on this.

Regards,
Dipti

admin's picture

Difference between what ?

saketbansal's picture

May be you are looking for this ...

Difference Between resource Leveling and smoothing

https://www.youtube.com/watch?v=2cN0xcjZEI4

I will go through your link and let you know incase of any qts

Hi DIpti,
Resource leveling relates to ensuring that your project team (or resources) are not overcommitted in the time constraints alloted.

Smoothing is looking at the the amount of slack available in our schedule AFTER leveling to ensure that you have used resources properly. http://www.izenbridge.com/blog/underlining-the-differences-between-resou... is a great article on this topic.

Resource leveling is used to make resources available in areas where necessary so as to not delay the critical path which would delay the project coming in on time.
Resource smoothing is used to make sure that the resources are scheduled to correspond with the work being done so as to not have recourses scheduled when there is no work to be done or when there is not enough work to require so many resources.
Remember, resources are people, equipment, supplies, etc..