work performance information ?

Question :
Work Performnace information is?
Answers :  
Progress and status of schedule activities
Adherence to quality standards
Status of deliverable completion
Forecasts

it is a tricky question as Work performance information is all about present condition, changes implementation & future planning at one shot.

seeing these options I feel it can be Status of delivery completion.

 I think it is option A.....

It has to be 'Status of deliverable completion.'  As per PMBOK 4th Edition page 453.

A.

 

Here is the good link that explains WPI and WPM.

http://pmstudycircle.com/2012/03/work-performance-information-wpi-vs-wor...

Thanks for that link. It has helped clarify many doubts.

 According to the link you provided it should be C not A

  • WPI is the ‘as of now’ status of the deliverables and WPM is a comparison between the actual status vs planned status.
cnppmp1's picture

C is thr ight answer

 

Regards
CN Patil

Thank you for posting your article. more posts!