What is indicated by an activity's late finish date?

A The latest the activity can finish without delaying a subsequent activity.

B  The latest the activity can finish without delaying the project.

C  The latest probable date that the ativity will finish.

D  The worst case, or pessimistic estimate for an activity.

Which option would be correct, I have  a provided answer, but let the suspence and interest be opened.

Actually it is not digesting to me.

Regards

 

B

Can you explain ? how?

As you know, Late finish date calculated from backward pass starting from project end date. Now you can figure it out.