Late Finish Date
Submitted by sspawar on Fri, 05/04/2012 - 12:32
Q
What is indicated by an activity's late finish date?
A The latest the activity can finish without delaying a subsequent activity.
B The latest the activity can finish without delaying the project.
C The latest probable date that the ativity will finish.
D The worst case, or pessimistic estimate for an activity.
Which option would be correct, I have a provided answer, but let the suspence and interest be opened.
Actually it is not digesting to me.
Regards
Forums:


diba_perfect
Fri, 05/04/2012 - 13:40
Permalink
B
B
sspawar
Sat, 05/05/2012 - 00:51
Permalink
Can
Can you explain ? how?
rdevaraj
Sat, 05/05/2012 - 02:21
Permalink
As you know, Late finish date
As you know, Late finish date calculated from backward pass starting from project end date. Now you can figure it out.