Help me with this question.
Submitted by sunitaPMP on Fri, 11/30/2012 - 21:00
I have difficulty with this question.Please see below.
Question:Which of the follwing is needed to develop detailed project cost estimate?
A. Management plan
B. Resource requirement
C. Project charter
D. Cost plan
Answer given is B.
So my understanding is this is "Estimate cost" process under Project Cost management.
I do not see resource requiremet is input to this process.
Can anyone explain how come Resource requirement is the answer .Please help me here.
Thanks


Scuba1
Fri, 11/30/2012 - 21:14
Permalink
Hi, I think the answer is
Hi, I think the answer is really in the wording of the other 3 options.
A. Management plan- there is no such thing as "management plan" as input to estimate cost
B. Resource requirement - "resources " are an input to estimate costs through Project schedule PMBOK 170
C. Project charter - the queston askes for "Detailed" project cost
D. Cost plan - there is no such thing as a "cost plan" as input to estimate cost
sunitaPMP
Fri, 11/30/2012 - 21:22
Permalink
Yes ,you are right.Human
Yes ,you are right.Human resource plan is the input for this process.So Resource requirement is the one.
Thanks for the reply...