 ________ is widely used to forecast project cost at completion

A. Cumulative CPI

B. Earned Value (EV)

C. Schedule Performance Index (SPI)

D. Total CPI

 I m goin with A

I guess, it is option B.

EV is used for forecast performance.

 

CPI, SPI, give a snapshot (todate) of cost and schedule performance.

Total CPI??

I'll go for EV (which is inclusive of EAC, ETC, & VAC for making forecasts).