________ is widely used to forecast project cost at completion
A. Cumulative CPI
B. Earned Value (EV)
C. Schedule Performance Index (SPI)
D. Total CPI
BK
Wed, 04/24/2013 - 16:33
Permalink
I m goin with A
ssundar
Wed, 04/24/2013 - 18:13
I guess, it is option B.
EV is used for forecast performance.
steelproject2012
Thu, 04/25/2013 - 00:23
CPI, SPI, give a snapshot (todate) of cost and schedule performance.
Total CPI??
I'll go for EV (which is inclusive of EAC, ETC, & VAC for making forecasts).
Thu, 04/25/2013 - 00:29
BK
Wed, 04/24/2013 - 16:33
Permalink
I m goin with A
I m goin with A
ssundar
Wed, 04/24/2013 - 18:13
Permalink
I guess, it is option B.EV is
I guess, it is option B.
EV is used for forecast performance.
steelproject2012
Thu, 04/25/2013 - 00:23
Permalink
CPI, SPI, give a snapshot
CPI, SPI, give a snapshot (todate) of cost and schedule performance.
Total CPI??
I'll go for EV (which is inclusive of EAC, ETC, & VAC for making forecasts).
steelproject2012
Thu, 04/25/2013 - 00:29
Permalink
CPI, SPI, give a snapshot
CPI, SPI, give a snapshot (todate) of cost and schedule performance.
Total CPI??
I'll go for EV (which is inclusive of EAC, ETC, & VAC for making forecasts).