EAC question

If the BCWS = $1,000,000, the BAC = $2,000,000, the ACWP = $1,500,000, the BCWP = $500,000 and you're halfway through the project after two years, what is the cost estimate at completion?
A. $2,000,000
B. $4,000,000
C. $6,000,000
D. $8,000,000
E. Cannot be determined without the EAC


 


 

 Ans: C

 

Formula used:

EAC= AC+ (BAC-EV/CPI) AND CPI= EV/AC

 eac = bac/cpi

ans : C