EAC question
Submitted by y0zh on Wed, 03/20/2013 - 08:09
If the BCWS = $1,000,000, the BAC = $2,000,000, the ACWP = $1,500,000, the BCWP = $500,000 and you're halfway through the project after two years, what is the cost estimate at completion?
A. $2,000,000
B. $4,000,000
C. $6,000,000
D. $8,000,000
E. Cannot be determined without the EAC
Forums:


BK
Wed, 03/20/2013 - 08:55
Permalink
Ans: C Formula used:EAC= AC+
Ans: C
Formula used:
EAC= AC+ (BAC-EV/CPI) AND CPI= EV/AC
ashshe24
Wed, 03/20/2013 - 18:21
Permalink
why complicate
eac = bac/cpi
ans : C