You are a project manager managing a construction project which is midway through the execution phase. The project is progressing well and is on time when one of the vendors informs you that a weeklong delay in his shipment delivery due to a law and order problem in his city. Which of the documents would best capture the impact of the delay on the project?
A)Network Diagram
B)Procurement Management Plan
C)Work Breakdown Structure
D)Risk Register
Forums:


crushPMP
Mon, 05/06/2013 - 16:12
Permalink
A? Network Diagram - as the
A? Network Diagram - as the critical path might change due to the delay and the near-critical path might become the new critical path (and hence the project duration) for the project.
vijayavadrevu
Mon, 05/06/2013 - 16:41
Permalink
Yes, the answer is A
Yes, the answer is A