document capturing impact of delay

 You are a project manager managing a construction project which is midway through the execution phase. The project is progressing well and is on time when one of the vendors informs you that a weeklong delay in his shipment delivery due to a law and order problem in his city. Which of the documents would best capture the impact of the delay on the project?

A)Network Diagram

B)Procurement Management Plan

C)Work Breakdown Structure

D)Risk Register 

crushPMP's picture

A? Network Diagram - as the critical path might change due to the delay and the near-critical path might become the new critical path (and hence the project duration) for the project.

 Yes, the answer is A