CPI & SPI
Submitted by desijattmunda on Mon, 12/28/2009 - 19:11
| 11. |
You found the following Earned Value Analysis information for a recently closed out project: SPI = 0.7, CPI = 1.0 |
|
| The project has been cancelled while it was executed. At that time the project was behind schedule and on budget. | ||
| The project's deliverables have all been finished. The project came in behind schedule but on budget. | ||
| The project's deliverables have all been finished. The project came in ahead of schedule but on budget. | ||
| The project's deliverables have all been finished. The project came in on schedule but over budget. | ||
I am Unable to undertand Why the answer is a)
b) can be answer too pl. can anyone explain ?
Forums:


ChandraR
Mon, 12/28/2009 - 19:27
Permalink
Schedule performance Index
Schedule performance Index (SPI) = EV/PV is an indicator whether the project is on time (SPI = 1) or behind the schedule(<1). Here SPI being 0.7 means the project got completed only 70% of the planned portion in the scheduled time i.e. the project is running behind the schedule.
Cost performance Index(CPI) = EV/AC is an indicator whether the project is incurring expenses more than(CPA<1)/less than(CPI >1)/ equal to (CPI = 1)the budget allotted at that stage. Here CPI = 1 means the Earned Value and Actual Cost incurred are equal.
Choice A is the only answer that satisfies both these criteria.
Chandra
desijattmunda
Mon, 12/28/2009 - 20:44
Permalink
thanks for the
thanks for the reply...
but both a) and b) say same thing behind schedule & on budget
exept
option a) project has been cancelled
option b) all devilerables have been finished
so which one to pick ?
ChandraR
Mon, 12/28/2009 - 22:30
Permalink
If the deliverables have
If the deliverables have been finished, your SPI = 1 (eventually) but here the SPI is explicitly stated as 0.7 i.e. only 70% of the planned work has been achieved so far. So there is still work (30%) to be done inorder to complete the deliverables. So choose A.
Chandra
desijattmunda
Tue, 12/29/2009 - 04:13
Permalink
Got it.... Thanks Mr.
Got it....
Thanks Mr. Chandra for the reply
desijattmunda
Tue, 12/29/2009 - 04:14
Permalink
Got it.... Thanks Mr.
Got it....
Thanks Mr. Chandra for the reply
Subhan
Sat, 01/08/2011 - 22:25
Permalink
If the question has not told that project closed, then answer?
In this question, its clear that project is closed and a low value of SPI is showing that all works are not completed, hence its terminated but what if the question has just given these SPI and CPI values without telling that project is closed. Does the answer remains the same, if Yes, how to determine that its canceled or our answer will become (b). Can any one explain.
pkukilla
Sun, 01/09/2011 - 02:11
Permalink
When the project is closed
When the project is closed EV-PV=0 whereas when the project is cancelled EV-PV wont be zero. Hope this make sense
Subhan
Sun, 01/09/2011 - 21:05
Permalink
When the project is closed
Still not,
you are right when project is closed EV - PV = 0, but this stage can be acheived during the project before closing, at any stage we can be earning same as much we have planned, at that stage EV - PV = 0 but project is not closed.
EV - PV not equal to zero, if terminated, that makes sense though.
Thanks, waiting ur reply.
cuongpt
Tue, 01/11/2011 - 04:23
Permalink
We use Elimination
We use Elimination approach:
SPI = EV/PV =0.7 <1 => EV< PV: project is behind the schedule
CPI = EV/AC =1.0 => EV=AC: project is on budget
(A) and (B) are sactified those condition.
Next, the project's deliverables could not be finished yet bcoz it's behind the schedule.
Therefore, A is correct answer.