What is the difference between schedule baseline and schedule mgmt plan

I am on risk mgmt, i see they are using schedule mgmt plan as input.

I don't see anywahere in time mgmt output of schedule mgmt plan.

Is this part of integration mgmt plan -  as a coponent representing schedule?

 

Thank you All. 

 

schedule and cost management plans are persumed to be created when you start construction of overall project management plan during first planning process. Both these plans represent game plan/rule book as to how to go about creating schedule and cost baselines / budget. Both baselines get updated into respective management plan, which in turn are part of overall project management plan

 

AG