Need Verification on a Question




A project manager divides the project into smaller
components. What are these components called?

A.     

WBS

B.     

Subprojects

C.     

Activity durations

D.     

Define activity

I read somewhere that when a project is broken down into
(WBS) each small activity becomes project of its own, so my answer would be B.
Could the answer be A and if it is why? Can some please explain?

My answer is WBS, WBS is the process of subdividing the project deliverables and project work into smaller, more managable component.

ref: PMBOK 4th edition secion 3.4.4 page 49 Create WBS

I also say it's wbs

I also say it's wbs

The question is asking the component, and as per tge definition WBS is the process.

My answer is Subprojects. As per Fig 5-8 of PMBOK guide 4.

The answer is WBS!

 Answer should be Sub Projects, since WBS is a process of decomposing scope.