Question- total duration b/w activities






















31.

Found this question on Oliver. Can someone pls explain.


Activity 1 has a duration of 20 days, Activity 2 of 10 days, Activity 3 of 5 days and Activity 4 of 6 days.



What is the minimum total duration between the Milestones A and B?

 

  36 days
  37 days
  39 days
  42 days

 



Activity


Dependency


Act Dur


Calendar days Assuming Act1 start day as 1st  


#Days in to the calendar


Acitvity 1


Act 1 can be started after reaching Mile stone A (FS)


20 d


1st to 20th


20


Acitvity 2


Act 2 can be started after Act1 is finished (FS)


10 d


21st to 30th


10


Acitvity 3


Act 3 can be finished 2 days before Act2  is finished (FF -2days)


5 d


Any 5 days between 21st & 28th


   0


Acitvity 4


Act 4 can be started 3 days after Act3 is finished (FS+3)


6 d


29th to 31th idle days.
Activity4 will be from 32nd to 37th


7
(-2+3+6)


Total


37 days

 Note:    Activity 3 is done in parallel with Activity 2 & getting finished before activity 2

Vijay Bheemineni, MS, PMP, ITIL.

Thanks again Vijay..

Kaam_wali_Bai's picture

Hello,


Why do we need to take  [-2] in account while calculating duration of activity 4? Activity 3 can be finished together with activity 2 and has 0 duration. Then all we have is FF+3 which will result in [6+3 =9] for activity 4


Activity A 


<----------------------------------->  


0                                              19                    = 20 days


Activity B


<----------------------------------->


20                                           29                   =  10 days


 


Activity C


<----------------------------------->


25                                          29                     = 0 days


 


Activity 4  [ 30,31,31 for lag time of 3]


<------------------------------------->                   = 3 days of leg + 6 days = 9 days


33                                            38


so total should be 39?


Can someone help here?

You have missed FF -2 for activity 3

Kaam_wali_Bai's picture

Why should I take FF-2 for Activity 3 into account when it is done in parallel with Activity 2?

Appreciating the persistence you put into your blog and detailed information you provide. I’ve bookmarked your site and I’m adding your RSS feeds to my Google account. storspelare casino

Im no master, however I trust you simply made a fantastic point. You unquestionably completely comprehend what youre talking about, and I can really get behind that. Iq option

Endeavor to join such blaze score site where livescore data is refreshed frequently to convey precise data to sports fans. livescores

This is information is very important in this present age. I learn so much form your post and thanks to share us. Canada Classified