Which of the following is NOT part of the Contract Closure process?
Forums:
There are currently 0 users online.
PMI, PMP and PMBOK are trademarks registered by Project Management Institute
Copyright © 2026,
Designed by Zymphonies

devgopi
Sat, 08/20/2011 - 20:32
Permalink
For me its B too.. acceptence
For me its B too.. acceptence already happend...moreover, all stakesholder also not require
ntgobinath
Sun, 08/21/2011 - 03:32
Permalink
Correct Ans: B
Look at the question. This is not talk about just closure, it's about 'contract' (procurement) closure.
A. Yes, Applicable to verify whether all the contracted work has been met.
C. Paying the final payment to contractor holders
D. Lessons learned from the contract agreement and procurement process
Question state which is 'NOT', So correct answer is B. This is about roject closure.
kunal.kishore123
Sun, 08/21/2011 - 07:51
Permalink
Correct answer is (B)B
Correct answer is (B)
B Obtaining formal acceptance of all deliverables from all stakeholders
We don't need to get approval from "ALL" stakeholders.
The catching point is "ALL".
rkmoosad
Sun, 08/21/2011 - 08:28
Permalink
Correct Answer is B.. PMBOK 12.4.3.2
Deliverables acceptance is usually done by authorized procurement administrator. Acceptance from all stakeholders are not required. PMBOK (4th Edition) 12.4.3.2
sumedha82
Sun, 08/21/2011 - 13:06
Permalink
Thanks guys..This explains...