SImpli learn question
Friends,
Below is a mock test question. Shouldn't be the answer be "C" as per Rita's Book. The actual answer seems to be D which I doubt.
Secondly whenever these kind of questions come in the exam, do we specifically need to look for the impact on triple constraints in the choices,else go for the next option,leaving out the option with impact on only constraint as given below. How do we approach this. Help please!!!!!
| QUESTION: YOUR ARE MANAGING A SOFTWARE PROJECT WHICH IS DUE FOR DESIGN DOCUMENT RELEASE NEXT WEEK. YOU ARE CURRENTLY REVIEWING THE DOCUMENT, WHEN AN INFLUENTIAL STAKEHOLDER ASKS YOU TO ADD A FEATURE TO THE EXISTING DESIGN. THIS STAKEHOLDER HAS EARLIER ALSO TRIED TO BOTHER YOU WITH UNREASONABLE DEMANDS AT THE LAST DAYS OF RELEASE. WHAT IS THE BEST YOU CAN DO IN THIS SITUATION? |
| OPTIONS: |
| A. REPORT HIS BEHAVIOR TO THE SENIOR MANAGER SUGGESTING THEM WHY HE SHOULD NO LONGER BE ASSOCIATED TO YOUR PROJECT AS A STAKEHOLDER |
| B. AS THIS PERSON IS INFLUENTIAL, YOU HAVE NO OPTION BUT TO LISTEN TO HIM AND ADD THE FUNCTIONALITY |
| C. DETERMINE THE IMPACT OF THIS CHANGE ON YOUR SCHEDULE AND THEIR CONSTRAINTS BEFORE TAKING A DECISION |
| D. ASK HIM TO RAISE A WRITTEN CHANGE REQUEST FORM AND THEN FOLLOW INTEGRATED CHANGE CONTROL |


admin
Sat, 08/20/2011 - 11:27
Permalink
D is correct option. Even
D is correct option. Even before you start evaluating the change, it should be formal and written and it should follow the change control process outlined for your project.
Regards
Patta
Sat, 08/20/2011 - 12:43
Permalink
Thanks Admin. So if there
Thanks Admin. So if there are 2 choices one of which says about formal written change request and other which talks about impact on triple constraints , I think we need to choose the first option as per the process.Am I right??
Thanks
Patta
admin
Sun, 08/21/2011 - 11:49
Permalink
In this context where the
In this context where the project is nearing completion and the stakeholder was troublesome its correct to tell him that let go the formal route.
But yes if you determine that Change submitted is not formal then you should ask for written CR then start doing impact assessment.