Random Questions 2

Q2 : Project Schedule control is concerned with all the following EXCEPT:

1. Influencing the factors that create schedule changes

2. Determining the the project schedule has changed

3. Determining planned start and finish dates for project activities.

4. Managing actual schedule changes as they occur

 

 2. Correct Choice: 3

Justification: Project Schedule Development, an iterative process, determines planned start and finish dates for project activities

This is simple

You plan the start and finish dates During planning and not during Controlling