Found this question in the head first exam.
32. Which of the following contracts has the MOST risk for the buyer? A.
Cost plus fixed fee (CPFF) B. Time and Materials (T&M) C. Cost plus award fee (CPAF) D. Fixed price (FP)
Answer given is (B), however according to Rita it should be (c).
Forums:


Emmanuel
Tue, 08/09/2011 - 23:12
Permalink
Head First Question - help needed
Yes the answer should be Cost Plus Fixed Fee because the buyer will have to pay for any additional material that is needed for the Project. As a result the burden is on the buyer.
admin
Wed, 08/10/2011 - 04:08
Permalink
What is Rita's explaination
What is Rita's explaination for option C ?..
nidhitripathi
Wed, 08/10/2011 - 10:07
Permalink
Rita doesn't have this
Rita doesn't have this question as such but there is a table in Rita which mentioned the types of contracts in decreasing order or risk for the buyer according to which CPAF is above T&M.
fwdkhan1
Wed, 08/10/2011 - 10:35
Permalink
From left to right Buyer
From left to right Buyer Risks
CPPC -> CPFF -> CPAF -> CPIF -> T&M -> FPEPA -> FPIF -> FP
From right to left Seller Risks
Ref. Rita Page 437
aaron
Wed, 08/10/2011 - 17:26
Permalink
Correct answer should be
Correct answer should be A (CPFF)
In CPAF the seller has some incentive to control the costs but not in CPFF.
All of the CR contracts carry more cost risk than T&M and FP (probably because CR contracts usually have large initial investments)