PMP Question
Submitted by munishmsh on Fri, 07/29/2011 - 07:11
You are a project manager of a construction company. You want to know with whom you will be communicating during the project. Which of the below document you
should refer to?
1.Project Plan
2.Scope Statement
3.Statement of Work
4.Project Charter
Forums:


rahultoraskar
Fri, 07/29/2011 - 07:21
Permalink
Hi Munishmsh,Project Plan
Hi Munishmsh,
Project Plan should be the correct answer as it integrates all different plan, including communication plan. The communication plan will have information related to the stakeholders and their communication details.
Regards,
Rahul
RP
Fri, 07/29/2011 - 07:28
Permalink
If you had mentioned that
If you had mentioned that Option 1 was a Project Management Plan, I would have chosen that as we know that the Comms Mngt Plan and many others sit in there.
In these regards, I would choose the Project Charter as it usually includes the stakeholders and their general requirements. Also note that stakeholder identification is a constant process and happens pass just the initiating and planning groups.