please help answer this TRICKY question from i2m Management Services
Submitted by PMPBOY on Thu, 07/07/2011 - 01:12
Question: approved change requests and approved corrective actions are an output of which of the following processes:
A. Performance Control
B. Quality Control
C. Manage Stakeholders
D. Risk Monitoring and Control
I selected 'D' but they said that the correct answer is 'C'.
PMP Experts please clarify how correct answer should be C.
Forums:


admin
Thu, 07/07/2011 - 04:34
Permalink
I dont think the question is
I dont think the question is correct, It should be "NOT an output" then the answer would be C. But still managing stakeholders may result in some Changes so there is a think line here
Its important to solve questions only from reputed sources, otherwise you will end up wasting your time and it wont be of any help to you in clearing the final exam.
Akshay Singh
Wed, 07/20/2011 - 14:51
Permalink
Question need to be framed
Question need to be framed differently. Change request may result from multiple processes including manage stakeholders..
As per PMBOk Manage stakeholder expectations may result
in a change request to the product or the project . It may also include corrective or
preventive actions as appropriate.
But change request approval is done during perform Integrated change control.
Brgds
Akshay Singh