To calculate EAC based on the cumulative COST & SCHEDULE performance...
Submitted by PMPBOY on Tue, 06/28/2011 - 18:11
Admin or PMP experts, please confirm if the
formula for calculating EAC based on the cumulative COST & SCHEDULE performance is:
PV + EV / [CPI x SPI]
Thanks,
PMPBOY
Forums:


rishiarien
Wed, 06/29/2011 - 06:18
Permalink
EAC based on cumulative cost and schedule performance
Wouldn't call myself a PMPExpert but EAC=AC+[(BAC-EV)/(CPIxSPI)]. I am not sure where you got the above formula from
hakim_mudassar
Thu, 07/14/2011 - 21:30
Permalink
wow, these formulae seem to get wierder by the day
Well I dont understand from where u both got the formulae from, but If you could possibly provide the problem statement I can assure you I can definitely get you the solution in an elaborative step by step simplified way:)