Please help answer this question as PMPBOY is stumped...
Submitted by PMPBOY on Sun, 06/26/2011 - 22:35
Question (from CheetahLearning):
Overworking and rushing through the requirements to meet the project objectives may result in the
serious negative consequences in the areas related to:
1. Costs
2. Scope
3. Control Schedule
4. Quality
Forums:


admin
Mon, 06/27/2011 - 03:55
Permalink
Quality, Which will inturn
Quality, Which will inturn have domino effect on schedule and cost
Akshay Singh
Wed, 07/20/2011 - 14:58
Permalink
Quality will go down
Brgds
Akshay Singh
akshay@emensuslearning.com
www.emensuslearning.com