Oliver Lehman free sample 75 questions
Submitted by ramaj on Thu, 05/12/2011 - 05:23
Hi,
I tried Oliver Lehman free sample 75 questions. It had lot many terms which i have not even studied in PMBOk and RIta.
1.RTY
2. Whistle-blowing
3.Liquidated damages
4.SMART objectives
Can anybody comment?
Thanks,
Rama
Forums:


admin
Fri, 05/13/2011 - 04:25
Permalink
Hi Rama,I would say its
Hi Rama,
I would say its important to know some of these terms if not all. All of the above are very common in project management so it will good to know these
REgards
muammerc
Fri, 11/11/2011 - 11:53
Permalink
Detail
RTY is Rolled Throughput Yield
http://www.six-sigma-material.com/Rolled-Throughput-Yield.html
http://lssacademy.com/2007/09/12/calculating-rolled-throughput-yield-rty/
SMART stands for Specific, Measurable, Achievable, Realistic and Time
http://en.wikipedia.org/wiki/SMART_criteria