Question- PERT
Submitted by sumedha82 on Tue, 09/13/2011 - 15:07
Another question from oliver.....Pls help (Apologies for the format)
A project manager made 3-point estimates on a critical path and found the following results:
| ||
| App. 4.2 days | ||
| App. 5.2 days | ||
| App. 6.2 days | ||
| You can not derive the path standard deviation from the information given. | ||
Forums:



bheemineni
Wed, 09/14/2011 - 02:22
Permalink
Answer is “B” = 5.2 days
Task Variance = [(P-O)/6]2
Project Standard deviation= √Sum of task Variances
Standard deviation of the allover path = √ [Var A + Var B + Var C + Var D + Var E]
= √ [(24-12)/6 2+ (14-8)/6 2+ (27-15)/6 2+ (28-10)/6 2 + (35-17)/6 2]
= √ [22+ 12+ 22+32+32]
= √ 27 = 5.196
Sorry if the symbols are not clear. I hope it still makes sense.
Vijay Bheemineni, MS, PMP, ITIL
RP
Wed, 09/14/2011 - 06:49
Permalink
I despise Oliver Lehman's
I despise Oliver Lehman's questions a whole lot. Did it during my prep but felt that during the actual exam, it was a serious waste of my time. If its anything to go by, you will not get such questions that require such detailed calculations. I have liaised with other colleagues and from our point of view, Oliver's questions just don't have any applicability to the actual exam.
sumedha82
Wed, 09/14/2011 - 10:07
Permalink
Thanks
Thanks Vijay for the detailed explanation.
Thanks RP for the heads-up.
pmalik
Fri, 09/22/2017 - 08:30
Permalink
PERT
For help in answering your question you can read the following articles:
How to use PERT, CPM and Standard Deviation Together?
What is the Use of Standard Deviation?
3-Point Estimate is Different From PERT