Changes to Procurements
Submitted by Dina Bekhit on Mon, 07/13/2015 - 12:22
Just I have a conflict ..
for any change that might be reguested for contract, will it be handled/approved through the Integrated Change Contol process (CBB) normally or through the Contract Change Control System ? And who might be involved in the committe?
Thanks :)
Forums:


gomsy
Mon, 07/13/2015 - 17:30
Permalink
Hi Dina,
Hi Dina,
Changes to a contract must first be agreed by all parties concerned, and follow the change control process outlined within the contract itself. Yes, first it will be in Contract Change Control and the ICC will look for the overall process of approval or rejection.
Below link has the very good explanation..
http://josephphillips.com/defining-the-change-control-system/
Dina Bekhit
Tue, 07/14/2015 - 05:55
Permalink
Thanks Gomsy for ur reply..
so that's mean, it will go through the Contract Change Control first (The procedure for handling Contract Changes) then will be oberlooked by the CBB for the final Approval/Rejection ! Am I right ?
gomsy
Wed, 07/15/2015 - 17:08
Permalink
Yep!
Yep!