Submitted by mwaqas on Tue, 04/21/2015 - 07:07
Q: While monitoring project risk, you find that an accepted risk is going to occur. Which of the following will you use to develop response?
A: Risk response plan
B: Fallback plan
C: Mitigation plan
D: Risk register
Two seperate sources have two different answers so it is confusing.
Forums:


dipti1pmp
Tue, 04/21/2015 - 13:50
Permalink
b
B: Fallback plan
mwaqas
Tue, 04/21/2015 - 14:21
Permalink
I thought of option b as well
I thought of option b as well but one explaination says we develop risk response plan to counter any risk happening. Hence during planning, risk response plan is developed and used during m&c... However other explaination says since it is an accepted risk, we have a fall back plan for it so we use that.
Still confusing as both explainations seem justified.
chinnasamy
Sat, 04/25/2015 - 08:25
Permalink
pmp
C. mitigation plan
its acceptable one
sudeep
Mon, 04/27/2015 - 11:03
Permalink
Risk Response Plan
As it is identified risk so to counter the identified risk we will refer the response plan.
So, my answer is - A
How to response a risk like plan -B, mitigate etc will be in Risk response plan. Pl. clarify if I am wrong .