question on conflict
Submitted by philzs on Mon, 03/30/2015 - 00:52
q25 Your subcontractor is 3 day late for delivery. To satisfy your customer tou reduced your cost. This is call:
Collaboration
compromise
forcing
smoothing
what do you think it is and why ?
Forums:


admin
Mon, 03/30/2015 - 03:27
Permalink
Its a compromise
Its a compromise
philzs
Mon, 03/30/2015 - 12:50
Permalink
Admin, thanks for your answer
Admin, thanks for your answer
this is what I tought also as it's a "loose-loose" because you lose = reduce cost, and it's late he lose
is it the way we have to get this one ?
I don't know why, the answer is Collaborate explanation : ( open dialogue that lead to a consensus )