Risk identification Question
During risk identification sessions, you and your team identified more than 150 risks for your project. You are afraid that evaluating each of these risks quantitatively will cost you an enormous amount of time, while not all of them are really relevant and important enough to justify such a measure. What should you do next?
o Identify risk triggers where possible. Analyze only those risks quantitatively for which no trigger could be found.
o Use qualitative risk analysis in order to prioritize risks for further action, such as quantitative risk analysis.
o Assess the probability of each risk qualitatively and further analyze only those risks with high probability.
o Assess the potential impact of each risk qualitatively and further analyze only those risks with high impact.
Wondering why Answer is 2 not 3
Can anyone please tell.
admin
Wed, 03/04/2015 - 04:52
Permalink
3 and 4 options separate out
3 and 4 options separate out Proablity and Impact
Option 2 says qualitative risk analysis which will consider both probablity and impact. So its more appropriate.
Smart_Charming
Wed, 03/04/2015 - 05:28
Permalink
Thanks for reply.
Ok .
Thanks
coolpmp69
Wed, 03/04/2015 - 14:09
Permalink
option 2 is correct because
option 2 is correct because after risk identification, one has to identify the risks that has high probability and impact on the project so you do qualitative risk analysis of all of them.
After this stage, you will get another set of high risks which will be then fed into quantitative analysis process to determine the most critical ones that can hamper your project.
nandita
Sun, 03/22/2015 - 00:49
Permalink
answer should be
answer should be
Use qualitative risk analysis in order to prioritize risks for further action, such as quantitative risk analysis.
This covers both imapct and probablity .
Mirza Riaz Ali Baig
Sun, 03/22/2015 - 06:26
Permalink
CAPM Mock test Scoring
Dear Admin,
Am getting 69% to 72% for CAPM exam from rita and free PMSTUDY test.
Please advice if am i ready to attempt the real exam.