Question on - Quality Audits
116. A project customer and a contractor agreed on regular quality audits during execution by a third party audit team, which is working on an assignment for the customer. What should the contractor have prepared for the audits?
1 Work results
2 Measurements and test results
3 Quality documentation
4 Contract-related correspondence
Guys,
for this question, the right answer is 3 and I am not too sure what does Quality documentation is required for that.. but here is what I think of the other answer
1 = Probably for Quality control, not Quality Audit ? is that right ?
2 = Probably for Quality control, not Quality Audit ? is that right ?
3 = not too sure
4 = When there is claims and you want to document the agreement or development, so nothing with Audits
any one ?
thanks


babai
Tue, 01/27/2015 - 10:49
Permalink
Amazing pmbok. Every time i
Amazing pmbok. Every time i realize that it is not in line with my logic.
Definition is: Quality Audits. A quality audit is a structured, independent process to determine if project activities comply with organizational and project policies, processes, and procedures.
It is not mentioned there, but seems like Quality documentation = organizational and project policies, processes, and procedures.
How should i know that - there is no Quality documentation definition in pmbok. It can be whatever.
imho 1,2,4 are applicable as well as the question doesn't ask any "most" or "first"
1. Auditor may check if work results are properly handled and documented, if change requests are correctly implemented
2. Auditor may check if measurements and tests were done with determined level of correctness
4. Audit of communication policies may be a part of quality management process
philzs
Wed, 01/28/2015 - 18:14
Permalink
thnaks
thnaks
what do you think from my understanding...
i tought 1-2 are more for quality control, as it verify Result not process
and 4 are more for issue in procurement
thanks
babai
Thu, 01/29/2015 - 07:25
Permalink
Not exactly in my opinion.
Not exactly in my opinion.
Quality management covers all processes, policies and procedures including procurement.
Procurement audit covers only closure.
Catherine S Porath
Tue, 02/06/2018 - 14:32
Permalink
The college essay writing
The college essay writing services information helped me a lot while making my presentation. I have taken a lot of help from here and one of the best things about. The method or concepts you have used are really easy to understand.