jwhelan
Sat, 11/22/2014 - 00:22
Permalink
if the project was closed you know it was terminated and not complete becuase if the project closed at completion the SPI qould be 0. I would say it was terminaded becuase it was behind schedule.
signor_rk
Sun, 11/23/2014 - 13:50
SV could be 0 (zero) at project completion. SPI can not be zero.
Regards.
Mon, 11/24/2014 - 02:51
I was thinking SV, then SPI should be 1 at completion.
jwhelan
Sat, 11/22/2014 - 00:22
Permalink
if the project was closed you
if the project was closed you know it was terminated and not complete becuase if the project closed at completion the SPI qould be 0. I would say it was terminaded becuase it was behind schedule.
signor_rk
Sun, 11/23/2014 - 13:50
Permalink
hi jwhelan
SV could be 0 (zero) at project completion. SPI can not be zero.
Regards.
jwhelan
Mon, 11/24/2014 - 02:51
Permalink
you are correct
I was thinking SV, then SPI should be 1 at completion.