Risk Management Query

PM identifies a risk of heavy storm in coming months which might affect the construction activity. What best PM can do?

A) Capture risk in risk register
B) Actively accept the risk and allocate time and cost reserve in contingency fund

Please answer.

admin's picture

Should be B - you will have to accept the risk and allocate time and cost reserve for damage done by storm.

But once the risk is identified, should we not immediately update in risk register?

Please clarify

admin's picture

I read the question as what is the best thing PM can do , you are right risk register can be updated, but B seems more appropriate answer