Approved change requests
Submitted by Sam82 on Mon, 09/15/2014 - 13:56
Approved Change Requests are output of: 4.5. Perform integrated change control.
And they are inputs to 3 processes:
1- 4.3 Direct and manage project work
2- 8.3 Control Quality
3- 12.3 Control Procurements
What do we do with the changes after they are approved?!
1- We send them all to 8.3 then to 4.3 ?
2- Some of them goes to 8.3 then to 4.3 and some to 4.3 directly ?
3- How 12.3 is related ?
Please support,
Forums:


slashinv
Wed, 09/17/2014 - 06:02
Permalink
I think the answer 1 should
I think the answer 1 should be the most appropriate.
12.3 should refer to approved CR with respect to any changes with procurement
Sam82
Wed, 09/17/2014 - 13:22
Permalink
Yes mate, I also think so,
Yes mate, I also think so,
admin
Wed, 09/17/2014 - 11:14
Permalink
After the change request is
After the change request is approved, assume its a scope change then it will goto 4.3 - direct and manage project work
If the change is tighten the Quality control by adding more tests then it will goto 8.3
Due to a change you may need to procure a resource, say you need earth moving equipment, then it will goto 12.3
Change request can be for any one of the project's triple constraint.
Scope, schedule, Quality = this will also impact the cost either positively or negatively
Sam82
Wed, 09/17/2014 - 13:32
Permalink
Thank you very much as you
Thank you very much as you make things more clear. But, isn't everything related to quality and anything we must change should pass after approval by quality to double check it, even if it is scope change ?!
Scope changes still needs to pass by quality to determine the quality measures for example,
what do you think?
slashinv
Fri, 09/19/2014 - 06:45
Permalink
Hi Sam82
Hi Sam82
you are right. quality should be built in and not measured. I hope this helps to choose the most correct answer !