what is burn rate?
Submitted by Raavi on Sat, 12/11/2010 - 20:15
87. A project was assessed and the following Earned value data have been found: PV: $750,000 EV: $750,000 AC: $900,000 What is the Burn rate of the project?
o 1.20
o 1.10
o 1.00
o 0.83
Forums:
sv
Sat, 12/11/2010 - 21:56
Permalink
BURN RATE=1/CPI
BURN RATE=1/CPI
cuongpt
Wed, 12/15/2010 - 09:22
Permalink
BURN RATE=1/CPICPI = EV/AC=>
BURN RATE=1/CPI
CPI = EV/AC
=> Burn rate = AC/EV = 900,000/750,000 = 1.2
Sandy10001
Wed, 08/20/2014 - 16:21
Permalink
Burn rate vs EVM
Perhaps part of your question has to do with understanding the relationship between burn rate and Earned Value Management. PMI has an article on this topic. It's free if you are a member. Please see http://marketplace.pmi.org/Pages/ProductDetail.aspx?GMProduct=00100294501 for more information.
Frances Tessler
Wed, 08/20/2014 - 20:55
Permalink
EVM
CPI is 1 so if they are asking about Burn Rate not sure this is the answer.
pmalik
Fri, 09/22/2017 - 09:10
Permalink
EVM Question
This is an EVM Question. For help in answering these questions you should read the following articles:
Earned Value Management Formulas
Estimate to Complete – 3 ETC Formulas For PMP Exam
Earned Value Management System Explained in Easy Language
To Complete Performance Index – TCPI Formula & Calculations Explained
Estimate At Completion – 5 EAC Formulas for PMP Exam
Basics of Earned Value Analysis