Earn value calculation (EAC)
Submitted by henrypmp123 on Sun, 02/10/2013 - 14:36
From online practice question:
Actual cost = $1000, Budget at completion = $800, cost performance index = 0.5,
Earned value = $600, the variance can occur again. The estimate at completion is:
A) $1000
B) $1400
C) $800
D) None of the above
Could anyone help, thanks a lot!
Forums:


daso
Sun, 02/10/2013 - 14:57
Permalink
D) None of the above
Since cost variances will continue: EAC=BAC/CPI=1600
steelproject2012
Mon, 02/11/2013 - 14:56
Permalink
Actual cost = $1000, Budget
Actual cost = $1000, Budget at completion = $800, cost performance index = 0.5,
Earned value = $600, the variance can occur again. The estimate at completion is:
A) $1000
B) $1400
C) $800
D) None of the above
Pls I would like to ask other would-be contributors:
(i) what does the term Budget at completin refer to? (BAC?)
(ii) If CPI=0.5, hw come EV=1,000; AC=6,000 as given: CPI=EV/AC = 600/1000= 0.6
daso
Mon, 02/11/2013 - 16:11
Permalink
<<what does the term Budget
<<what does the term Budget at completin refer to>>
please consider reading PMBPOK chapter on EVM
sspawar
Mon, 02/11/2013 - 15:42
Permalink
wrong question,
wrong question,
sunku65
Sat, 06/07/2014 - 08:46
Permalink
It is a wrong question, thats
It is a wrong question, thats why select choice D.
signor_rk
Sun, 08/10/2014 - 07:19
Permalink
Considering the same CPI
What about this case:
EAC= AC + (BAC-EV)/CPI
= 1000 + (800-600)/0.5
= 1000 + 200/0.5
= 1000 + 400
= 1400
So option # (B)