Does any any one agree with this number?

Which of the following is not a technique to plan communication in the project?

A)Communication Requirement Analysis
B)Communication Management Plan
C)Communication Methods
D)Communication Technology
Explanations:

Answer (b) Communication Management Plan. The communication management plan is an output of the plan communication process. In order to find out more about the project communication management knowledge area, please refer to Lesson number 10 of Simplilearn PMP Preparation Course.

admin's picture

Straightforward question, not sure what is the doubt here.

B is not a technique is a Management Plan.