If EV = 50; PV = 60; AC = 55 and the current cost performance is likely to continue into the future, what is the likely variation in the overall cost at the end of the project?
a.Insufficient information
b.0.1
b.0.2
d.-0.1
Explanations:
Answer (b) Based on the EV and AC values, it seems that there is a 10% escalation in the cost. Given that this trend is likely to continue in the future, the project will also end up with a 10% cost escalation
Forums:
admin
Thu, 07/17/2014 - 03:07
Permalink
Questions and answer
Questions and answer explanation given seems to be enough. There is 10% variation in cost which is likely to continue as per the question. So at the end of the project there will be 0.1 cost variation which is 10%.
sunku65
Thu, 07/17/2014 - 07:30
Permalink
Assume BAC = X
Assume BAC = X
CPI=EV/AC=50/55 = 0.90
EAC= X/.90
VAC = x- x/.90
VAC = (.90 X -X)/.90 = X(.90-1)/.90 = X(.10/.90) = 0.11=11%
sunku65
Thu, 07/17/2014 - 07:33
Permalink
your options looks wrong.
your options looks wrong.
Look a,b,b,d and both options having 0.1
vandana singh
Thu, 07/17/2014 - 11:59
Permalink
Thanjks Sudku I got it