Confusion (Weak Matrix vs Functional)
Submitted by farhanmazhari on Tue, 05/13/2014 - 07:37
Hi All,
Can anyone explain the difference between weak matrix and functional structure. The PM is coordinator or an expeditor in both structure? what is the difference?
Forums:


sunku65
Tue, 05/13/2014 - 08:27
Permalink
Weak matrix is very close to
Weak matrix is very close to the functional organization.
The PM functionality is the same as Functional Organization.
Some other benifits have the TEAM in matrix organization compare to Functional Organization structure.
--- can get the highly skilled personnel they require.
--- resources can be shared between FO depts. and other projects.
--- efficiency of Matrix organizations is higher.
--- Profeessionals can develop their career.
farhanmazhari
Tue, 05/13/2014 - 08:48
Permalink
There is a question which
There is a question which confuse me.
Q: The Project Manager acts as a coordinator or expeditor in.
A: Weak Matrix
B: Strong Matrix
C: Functional
D: Projectized
Answer is: Weak Matrix
I thought its Functional
sunku65
Tue, 05/13/2014 - 11:45
Permalink
In Weak Matrix by default the
sunku65
Tue, 05/13/2014 - 11:49
Permalink
In Weak Matrix by default the
In Weak Matrix by default the Project Manager acts as a co-ordinator or expeditor.
Whereas in Functional Organization by default the PM has no role at all. Even if he exists, PM role will be very limited and he has to ask the Functional Manager for his requirements. We never know whether the PM may have a staff assistant, Coordinator or expeditor role until Functional Manager says.
Sandy10001
Wed, 09/10/2014 - 14:05
Permalink
Weak Matrix
For this question, the correct answer is the Weak Matrix. In a Functional Organization, PMI uses the term 'expeditor.' The PM isn't even acknowledged.
saurabhkalra
Tue, 05/13/2014 - 14:37
Permalink
PM role
The role of PM in weak matrix is that of expediter or coordinator. PM might not even exist in functional matrix
Frances Tessler
Sun, 09/14/2014 - 00:32
Permalink
Functional vs Weak
In a weak matrix the PM can be either a Coordinator with some decision or a Expeditor with no decision making.
In a Functional Work Environment he is just a Expeditor with no decision making ability.