Two answer of question from a R.E.P, what do you think?

PMP Fighter's picture

1.You have been managing a project for creating special designs for the seat covers for the luxurious cars. You are asked to select tools and techniques to implement a quality assurance process, to supplement existing quality control activities. Which of the following would you choose?

A. Quality audits.
B. Statistical sampling.
C. Pareto diagrams.
D. Trend analysis.

I choose B, but answer is A.

The Explanation :
According to PMBOK, Quality Audit is a tool for quality assurance.
Hence choice A is correct while choices B, C, and D are incorrect.

2. You are working on a project that is about to conclude. Your organization is a functional organizational. The project's functional employees tend to concentrate more on the potential future assignments than on the current one.

What type of needs, from the following, are the employees trying to fulfill?

A. Physiological.
B. Need for Belongingness.
C. Security.
D. Need for Self-actualization.

I choose B ,but correct answer is C

The Explanation :
In this case employees would like to ensure that they have jobs. Hence they are trying to fulfill the need for 'security'.
Hence Choices A, B and D are incorrect.

Do you think the answer is reasonable?

question 1. Answer is A Correct.

Regarding Question 2. The employees goes back to Functional Organizations department back after closing the project.  Still, they have full time job.  Whereas no need think about security. Unless company has any policy saying that the emplyoyess always shoud be in the project.

IN the question ...more on the potential future assignments ... words drags to select Answer Security other wise something else to choose the different answer.

Let's see wait and see others openion.

 

admin's picture

Firstly  I dont think quesitons like 2. will come in Real exam. But after reading the explaination Security seems the correct option. 

Q1 - Answer is quality audits.