Why “manage project team” and “manage stakeholder” are in “project Executing group”?
Submitted by PMzilla_binh on Thu, 12/09/2010 - 00:06
Just wonder why those 2 processes are not in "monitor and control" but in "Executing" group in PMBOK 4th?
I believe in order to carry out activity for 2 process, we need to do a lot of "Check & Act", so should it be in "monitor & control"?
Anyone can explain? Thanks
Forums:


cuongpt
Thu, 12/09/2010 - 07:54
Permalink
I have the same question.
I have the same question. Looking forward to hearing from you.
faisal khan
Mon, 12/13/2010 - 12:18
Permalink
there wont be any meaning
there wont be any meaning 'managing' project team or stakeholders in 'monitor & control' when the project gets executed in the wrong way at the first place.