Estimation Technique
Submitted by abishek10 on Fri, 03/07/2014 - 17:43
Which estimation Technique takes the longest time?
A: Parametric Estimating
B: Bottom-up Estimating
C:Three-Point Estimates
D:Project Management Estimating Software
Forums:


admin
Sun, 03/09/2014 - 17:32
Permalink
Bottom up , since its most
Bottom up , since its most detailed.
saketbansal
Tue, 03/11/2014 - 15:05
Permalink
Lot of time we get confuse
Lot of time we get confuse between bottom up and three point estimation... don't you think we end up using three point estimation while applying bottom up ?