Can PM approve change request which does not influence scope, time or costs?
Hi,
I'm studying for PMP, and I'm not sure what is PMP opinion about this question: can PM approve (without CR board) a change request, which don't influence scope, time or cost?
OK, I know what is the right procedure if change request influences those baselines, but what if it does not? What if PM analysis CR, which customer demands, and finds out that it does not have any impact to any project constraint? Does PM has the authority to approve this CR on his own?
I would say that still not, since this is a change from scope, contract etc., no matter if it does not have any impact - it still needs to go through change request board for approval. I'm I right?
Tnx for help,
Urša


admin
Sun, 12/05/2010 - 06:42
Permalink
Can you give an example of a
Can you give an example of a CR, which will not have any impact to project constraint ?
In my opinion , it would not be a CR then, its a request and PM has authority to accomodate requests from customer.
Regards
Admin
urskah
Sun, 12/05/2010 - 09:08
Permalink
I meant CR, which will not
I meant CR, which will not has negative impact on schedule or cost - it will not prolong schedule or increase cost, but it is a great importance to customer.
So, can PM accept a change, which is very important to customer, and will not have negative impact on mentioned constraints?
I think, that this is still CR which has to follow the same proces like other CR's (change control board etc.), but I'm not sure. I also think that for PMI situation is goldplatting. Am I right?
admin
Mon, 12/06/2010 - 16:00
Permalink
hi UrskhahCan you think of
hi Urskhah
Can you think of some example where it would be a CR and still not impact schedule /cost or triple constraint ? I am trying to understand your question.
If it is important to customer it will have some impact on the project's triple constraint and PM cannot just approve the CRs without consulting the stakeholders .
urskah
Mon, 12/06/2010 - 21:31
Permalink
admin, example is that e.g.
admin, example is that e.g. customer wants work done to different procedure. This procedure won't impact the scope or cost or schedule, work can be done almost the same, it is also not requested by the contract how the work should be done. But, it was written in project documentation and agreed with customer that it will be used procedure A, but customer now wants procedure B. Can PM decide him self about accepting the change or should he send it through CR board?
I have found this question in one of online tests, but unfortunatelly I can't find again it to copy-paste it. Since answer was unclear, I just wanted to double-check it.
Maybe I comlicate it to much, now when I think again I'm convinced that it still needs to go through CR board...
Tnx and KR.
cuongpt
Thu, 12/09/2010 - 09:25
Permalink
Project could be broken down
Project could be layered in 3 levels as following:
Project Scope: deliverables> workpackages> activities
In my opinion, any changes that only impact at Activity level, PM can take it up on himself/herself. But the changes that impact at Work package level or higher, PM needs to get approval from Change Control Board.
I'd like to hear from you.
faisal khan
Sun, 12/12/2010 - 16:26
Permalink
answer?
ok, even if u couldn't find the source of the question, can u write down here what was that UNCLEAR answer !!!!!!!!!!
agm
Sun, 12/05/2010 - 14:14
Permalink
wondering how can a PMP
wondering how can a PMP aspirant post such a dumb question.
urskah
Mon, 12/06/2010 - 21:34
Permalink
Thanks to author of
Thanks to author of previous post, this is an extremely valuable contribution...it has just proved how very smart you are.
I have found here number of questions, some of them also unnecessary to me to, but some of us don't need to give such dumb posts, which help no one except maybe to author's ego. You could just hold this thought for your self, if you don't know the answer or don't want to share it or it is so obvious to you.
You know, wise people say, that there are no dumb questions...
faisal khan
Sun, 12/12/2010 - 16:29
Permalink
wow
exactly, there are no dumb questions but dumb people!!!!!!!!!!!!
agm
Mon, 12/13/2010 - 13:52
Permalink
frog's theory
It looks like this question was picked from frog's theory lol.....
faisal khan
Mon, 12/13/2010 - 16:46
Permalink
oooh
its great to know that there are other people who know about 'frog's theory'...!!!!
it seems, any time soon, it should get published & help the aspirants.....?!