Decomposition question
Submitted by bpp9614 on Tue, 11/16/2010 - 20:15
Decomposition is a valuable tool for Create WBS process. However, decomposition may not be possible for a deliverable or subproject if:
Choice 1 The deliverable or subproject is very complicated
Choice 2 The deliverable or subproject is already being produced
Choice 3 The deliverable or subproject will be accomplished far into the future
Choice 4 The deliverable is a service
Forums:


deepakadlakha
Wed, 11/17/2010 - 03:12
Permalink
just a guess...
Its just a guess, option 2. I am not an expert, i just started preparing for this exam. So its possible i may be wrong.
Option 4 can also be true but i am not sure.
PMzilla_binh
Wed, 11/17/2010 - 03:42
Permalink
Either option 2 or 4.However,
Either option 2 or 4.
However, I think the "being already produced" still possible to decomposed although they might not be meaningful while "a service" is diffcult to
So option 4
bpp9614
Sat, 11/20/2010 - 17:45
Permalink
Actual Ans is 3
The ser vice is certainly can be decomposed. I was confused between 2 and 3. Choice 2 talks the deliverable is being produced, means its already in Execution phase. Do we still decompose a prodcut in execution phase. Also being produced sometimes means its an operation not a project, where the product is produced on daily basis (factory).
pkukilla
Wed, 11/17/2010 - 18:29
Permalink
Ans is 3
Its an example of Rolling Wave Planning . Here deliverables are decomposed in to milestone level until more details are available for decomposing it in detail
cuongpt
Thu, 11/18/2010 - 05:06
Permalink
Rolling wave Planning is the
Rolling wave Planning is the technique applied in Time Planning when you start the projet without knowing alot about the work that you'll be doing later. It lets you plan and schedule only the stuff that you know enough to plan well, while Decompostion in the context of this question is used to divide Work scope( which covers all the you need to be done) into accountable and managable work packages.
Rolling Wave Planning:
+ Purpose: Time Planning
+ Knowledge Area: Time Mng
Decompositon:
+ Purpose: Work decomposing
+ Knowledge Area: Scope Mng
Pls correct me if I'm wrong
cuongpt
Thu, 11/18/2010 - 05:05
Permalink
Service is kind of on-going
Service is kind of on-going operation, so it's impossible to decompose a service into several smaller pieces. Correct me if I'm wrong.
bpp9614
Sat, 11/20/2010 - 17:43
Permalink
Service is not an operations !!! Clear the basics
Service can be an end result of a project. e.g you create a project to give transportation service in rural area by creating roads, buses etc. The end result is a transportation service.
The actual maintanance of this service is an operation e.g daily bus service, road cleaning etc.