Why Scope Baseline is not an Input in Verify Scope
Submitted by bpp9614 on Mon, 11/01/2010 - 18:49
I am applying logic to understand the inputs and outouts for each process and I am good till now. But there is a confusion in Verify Scope.
I strongly believe that Scope Baseline should be an input to Verify Scope. Else we are verifing scope against what (only requirements)? PMBoK says only inputs are Requirement Document (Why I need this, if everything is there in WBS). I agree on Requirement Treability document, because it traces where I have implemented the particular requirement.
-Bish
Forums:


pmpodcast
Mon, 11/01/2010 - 20:18
Permalink
Hi, Scope baseline is a
Hi,
cuongpt
Tue, 11/02/2010 - 03:56
Permalink
Scope Baseline (including
Scope Baseline (including scope statement/WBS/WBS dictionary) is created in order to figure out the scope of work and works need to be done to produce the deliverables.
The purpose of Verify Scope process is to get acceptance from the sponsor or customer for the deliverables by inspecting/reviewing the deliverables with their requirements presented in requirements documentation/requirements traceability matrix and PM plan.
That's why Scope Baseline is not necessary included in Verify Scope's Input.
Sincerely
CuongPT
vinaip (not verified)
Sun, 11/07/2010 - 13:56
Permalink
Scope Baseline and verify Scope
Scope baseline is an important input to verify scope. Read more about the Scope Baseline and PMP questions on Scope Baseline.
Cheers,
Vinai, PMP
sspawar
Fri, 07/20/2012 - 11:46
Permalink
scope baseline
Verify Scope
A genuine question
What is being verified ?
Answer - SCOPE - it means you need this as input from where - Scope Base Line, some body can say - that is only project Validated Deliverables.- it is again a part of project scope statement and it is output of Difine Scope.
By what these will be verified ?
Ans - All input other than Scope
The same thing is for CONTROL SCOPE too.